Project Status
The TWG has now completed Phase 1 of it project, which consisted of gathering and reviewing existing materials relating to ferry marshalling options. The Phase 1 report can be accessed through the link on this page below, along with supporting information. All documents cited in the report can be accsessed throught the "Resource Documents" link below.
A Public Meeting has been scheduled for Sunday, February 25th, 2007 to receive comments on the report.
The TWG is begining its work on Phase 2, in which the TWG is asked to "provide information to Council on the preferred size of ferry capacity options, improvements to the transit system, and transportation demand management alternative" (TWG Terms of Reference).
TWG Reports and Communications
During its work, relevant materials produced by the TWG or governing its work will be posted here. Most of them will also be available in paper form at the Bowen Library and at the Municipal Hall.
TWG Phase 1 Report December 2006: Ferry Marshalling Options for Snug Cove